House Roztoky

Project description

Within three weeks while the client was on holiday, we installed a new kitchen cabinet in his house including the delivery of a new floor covering. Prior to laying the covering, the uneven surface of the floor was levelled. The kitchen was painted, and a drywall suspended ceiling built. We installed wiring for the whole kitchen. We also replaced the doors in the house. Being happy with our performance, the client later ordered complete reconstruction of his terrace attached to the house. As to the terrace, we removed useless floor layers, tiles and all plating and lining including the staircase.

Date:

August 2018

Location:
Roztoky

Client:

private investor

Copyright ©

2024 Created by tritonit.cz. All rights reserved.